The rooms in front of the cave are for drying and brining the cheeses. This part of the building is three quarters below ground. In one of these rooms I hope to install a walk in cooler in the future.
The making room, cleaning room and office in the front are above ground. The cleaning room was added after I read the state regulations for dairy processing plants. State regulations prohibit cleaning milk containers in the making room when the milk is not produced on the premises. I do not intend to start a dairy but plan to make cheese from milk bought from local farmers.
The making room will get a cheese making vat in the center. Around the walls sinks and draining tables are planned.
I haven’t worked out the heating system for the building yet. Although the winters are long and cold in upstate New York, by building the structure in a hill from thick concrete walls insulated from the outside, I hope the building will not require a lot of heating. A small central hydronic system fired by propane might do. I hope I can use the same system to heat the water for the cheese vat as well as other running water.
The plant has two septic systems as required by regulations. I will write about the septic systems in a separate post later. Being located in the New York City watershed adds an enormous amount of restrictions and regulations to these systems and makes building outside municipal systems often cost prohibitive. Whether this will be the case with my plans is to be seen.
5 comments:
unbelievable, jos. this is fantastic. best of luck with it all.
It looks like you are having fun with this plan. I hope you get to build this!
Good Drawings, only the first one is a thumbnail, bad quality, if you can fix it, please?!
I think I fixed it. Thanks for the note.
Hello Dude,
Beautiful presentation! 3D software plays an important role in Building models and plans. 3D animated building plans will be more effective than any other medium. Thanks a lot...
Post a Comment